13/04 - Development of Dargues Gold Mine - Progress in pictures (3rd Update)

With the finalisation of the ROM pad earthworks, excavation  of the box cut is happening apace.
 
Offsite, preparations are being made for the transfer of the first parts of the Bendigo infrastructure to Dargues this month.
 
Total workforce on site is currently 38 and this week we finalised the appointment of the project’s General Manager who will commence in May.