13/03 - Development of Dargues Gold Mine - Progress in pictures (2nd Update)

We have recovered from the challenging conditions resulting from the significant rainfall that occurred throughout NSW at the end of February.
 
The ROM pad earthworks have now reached their final level and the box cut excavation is starting to take shape with approximately 65,000 cubic metres of earth moved.
 
Final preparations are being made for the formal engagement of the construction contractor, having finalised the planning for relocation of Bendigo plant and infrastructure to Dargues.
 
A further six employees have been appointed to the project over the past few weeks - importantly, four of the six are local residents from nearby communities.
 